Roof replacement
Fee basis: Based on project value.
Project value for the formula: low $8,000, typical $12,000, high $22,000.
Portland Permitting & Development Building and Other Permits Fee Schedule, effective July 10, 2026 (source retrieved Oct 18, 2026). The cited schedule is the City of Portland Building and Other Permits Fee Schedule, effective July 10, 2026.
The Building Permit Fee on p.1, for total construction value from $2,001 to $25,000, is $220.85 for the first $2,000 plus $13.91 for each additional $1,000 or fraction thereof. Listed bands are the building-permit line plus the 12% Oregon surcharge only.
The 12% Oregon surcharge is charged on that building permit fee and is already inside each total, so it is not added again. Listed assumed valuations are $8,000 low, $12,000 typical, and $22,000 high.
The official typical project value is $12,000. Each listed valuation is inside the $2,001 to $25,000 Building Permit Fee band and is an exact thousand above $2,000, so no fractional thousand is added.
- Low $8,000 = $340.83 total.
That is 6 additional thousands: $220.85 + $13.91 x 6 = $304.31. 12% of $304.31 is $36.5172, which rounds to $36.52. $304.31 + $36.52 = $340.83.
- Typical $12,000: building permit $359.95 + Oregon 12% state surcharge $43.19 = $403.14.
That building permit line is 10 additional thousands: $220.85 + $13.91 x 10 = $359.95. 12% of $359.95 is $43.194, which rounds to the official surcharge of $43.19. $359.95 + $43.19 = $403.14.
The building-permit extra on this row is $359.95. Those two lines are the typical total.
They are not added a second time on top of $403.14. high $22,000 = $558.94 total. That is 20 additional thousands: $220.85 + $13.91 x 20 = $499.05.
12% of $499.05 is $59.886, which rounds to $59.89. $499.05 + $59.89 = $558.94. The Development Services Fee - Commercial on p.2 is the Commercial Development Services Fee, and it is not a building-permit line.
Do not call that fee, or its $4.69 per $1,000 rate, a building-permit line. In the $2,001 to $25,000 band that table is $44.79 for the first $2,000 plus $4.69 per additional $1,000.
The $4.69 per $1,000 rate is not used in the $340.83, the $403.14, or the $558.94. The Residential Development Services Fee and the 65% plan review / process fee are still omitted, so real issued totals can be higher.
Building-permit line + 12% Oregon surcharge only. PP&D also charges plan review and other fees on the same July 10, 2026 schedule – those lines were not fully extracted, so real totals are higher.
City of Portland Building and Other Permits Fee Schedule, effective July 10, 2026 Retrieved Oct 18, 2026.