Building Permit Fees in Seattle, WA (2026)

Seattle Department of Construction and Inspections (SDCI) is the permit office for Seattle, WA. The fee schedule year is 2026.

Updated Oct 18, 2026 · Fees checked Oct 18, 2026

Permit fees by job

Building permit fees in Seattle, WA by job, 2026
JobPermit feeHow it is calculatedOfficial source
Roof replacement

Typical $742.97

Range $648.89 to $978.17

Based on project value. Project value for the formula: low $8,000, typical $12,000, high $22,000.

Full roof replacement calculation below

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2

Retrieved Oct 18, 2026

HVAC replacement

Typical $126.73

Range $63.37 to $190.10

Flat fee. Project value on this row: $7,500.

Full HVAC replacement calculation below

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Table D-8 (22.900D.090)

Retrieved Oct 18, 2026

Deck

Typical $1,059

Range $924.20 to $1,301

Based on project value. Project value for the formula: low $8,000, typical $12,000, high $19,200.

Full deck calculation below

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2

Retrieved Oct 18, 2026

Kitchen remodel

Typical $1,821

Range $1,159 to $3,097

Based on project value. Project value for the formula: low $15,000, typical $35,000, high $75,000.

Full kitchen remodel calculation below

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2

Retrieved Oct 18, 2026

How each fee is calculated

Roof replacement

Fee basis: Based on project value.

Project value for the formula: low $8,000, typical $12,000, high $22,000.

  • Typical $12,000: DFI $501 → building permit $501 + STFI plan review $200.40 (40% of DFI) + technology $35.07 (5%, SMC 22.900A.100) + WA BCC $6.50 (RCW 19.27.085) = $742.97 (Seattle SDCI 2026 Fee Subtitle Tables D-1 and D-2; STFI path: 100% building permit + 40% plan review of DFI; source retrieved Oct 18, 2026).
  • Low $8,000 valuation = $648.89 total.

That low band reconciles to whole-dollar DFI $437: building permit $437.00 (100% of DFI), plus STFI plan review $174.80 (40% of DFI), plus technology $30.59 (5% of the $611.80 permit and plan-review subtotal), plus WA BCC $6.50, equals $648.89. And high $22,000 valuation = $978.17 total.

That high band reconciles to whole-dollar DFI $661: building permit $661.00 (100% of DFI), plus STFI plan review $264.40 (40% of DFI), plus technology $46.27 (5% of the $925.40 permit and plan-review subtotal), plus WA BCC $6.50, equals $978.17. Each listed band is the STFI like-for-like reroof path.

The rule is a building permit at 100% of DFI, plus plan review at 40% of DFI, times 1.05 for the technology fee, plus the flat $6.50 WA BCC. Alternate path not used in listed totals: full plan review (200% of DFI) for structural changes or layered roofs when STFI is ineligible; confirm STFI eligibility with SDCI before filing.

Computed from official Table D-1 DFI × STFI rates (100% building permit + 40% plan review) + 5% technology (SMC 22.900A.100) + $6.50 WA BCC (RCW 19.27.085) using Seattle SDCI 2026 Fee Subtitle Tables D-1 and D-2 (retrieved 2026-10-18). Listed bands: low valuation $8,000 → $648.89; typical $12,000 → $742.97; high $22,000 → $978.17. Confirm STFI eligibility with SDCI; layered roofs or structural work may require full plan review (200% of DFI) – that alternate path is not included in the official typical/low/high.

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2 Retrieved Oct 18, 2026.

HVAC replacement

Fee basis: Flat fee.

Project value on this row: $7,500.

Like-for-like furnace/heat-pump swap uses the Seattle SDCI 2026 Fee Subtitle (SMC 22.900) Table D-8 (22.900D.090) mechanical equipment fee, not the valuation DFI (source retrieved Oct 18, 2026). Table D-8 charges a fixed per-unit amount of $60.35 for each forced-air furnace, heat pump, or similar unit, including ducts attached thereto.

The 5% technology fee under SMC 22.900A.100 is applied to that Table D-8 subtotal and is included in every listed band.

  • Low 1 unit is one forced-air furnace, heat pump, or similar unit, including ducts attached thereto: 1 × $60.35 = $60.35, plus the 5% technology fee $3.02 (SMC 22.900A.100), and $60.35 + $3.02 = $63.37.
  • Typical 2 units (furnace + AC or two heat-pump outdoor/indoor): 2 × $60.35 Table D-8 = $120.70; the official 5% technology fee is $6.04 (SMC 22.900A.100); the official total is $126.73, which matches the official path 2 × $60.35 × 1.05.

That $120.70 is the Mechanical equipment fee (Table D-8) extra on this row, and that $6.04 is the Technology fee (5%) extra; both are included in the typical fee, so they are not added again.

  • High 3 units is three units on that same per-unit Table D-8 basis (forced-air furnace, heat pump, or similar, including ducts attached thereto): 3 × $60.35 = $181.05, plus the 5% technology fee $9.05 (SMC 22.900A.100), and $181.05 + $9.05 = $190.10.

The low, typical, and high bands are therefore 1 × $60.35 × 1.05 → $63.37, 2 × $60.35 × 1.05 → $126.73, and 3 × $60.35 × 1.05 → $190.10. The per-unit charge covers ducts attached to that equipment; this row is not the Table D-2 valuation path.

Excluded from these totals: a separate Table D-14 / OTC electrical permit if new circuits or disconnects, and new duct systems submitted separately, which use Table D-2 (valuation) instead of the Table D-8 per-unit mechanical equipment fee. Amounts for those alternates were not listed as fee lines.

Confirm path with SDCI.

Like-for-like furnace/heat-pump swap is a mechanical equipment fee (Table D-8 / 22.900D.090), not the valuation DFI, using Seattle SDCI 2026 Fee Subtitle (retrieved 2026-10-18). Listed bands: low 1 unit $60.35 × 1.05 tech → $63.37; typical 2 units 2 × $60.35 × 1.05 → $126.73; high 3 units 3 × $60.35 × 1.05 → $190.10 (SMC 22.900A.100 technology fee included). New duct systems submitted separately use Table D-2 (valuation) – that alternate path is not included in the official typical/low/high. Separate electrical (Table D-14 / OTC) is extra and is not listed here.

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Table D-8 (22.900D.090) Retrieved Oct 18, 2026.

Deck

Fee basis: Based on project value.

Project value for the formula: low $8,000, typical $12,000, high $19,200.

  • Typical $12,000: Tables D-1 and D-2 set DFI at $501 (Seattle SDCI 2026 Fee Subtitle, SMC 22.900; source retrieved Oct 18, 2026).

On the official path the building permit is 100% of DFI and plan review is 100% of DFI. That is the full plan-review path: 100% building permit + 100% plan review of DFI, or 200% of DFI.

Building plus plan review is the $1,002 building+plan subtotal. The technology fee is 5% of that $1,002.

The WA State Building Code Council fee is a flat $6.50 when a building permit is issued, at low, typical, and high. Add the official pieces: DFI $501, building permit $501 + plan review $501 (100% of DFI) + technology $50.10 (5%, SMC 22.900A.100) + WA BCC $6.50 (RCW 19.27.085) = $1,058.60.

That is the official typical fee at the $12,000 typical project value.

  • Low $8,000 valuation = $924.20 total ($437 building + $437 plan + $43.70 tech + $6.50 WA BCC).

At $8,000 the DFI is $437. Building permit $437 plus plan review $437 is $874.

Technology is 5% of $874, which is $43.70. Add the flat $6.50 WA BCC and the low total is $924.20.

The high $19,200 valuation = $1,300.52 total ($616.20 building + $616.20 plan + $61.62 tech + $6.50 WA BCC). At $19,200 the DFI is $616.20.

Building permit $616.20 plus plan review $616.20 is $1,232.40. Technology is 5% of $1,232.40, which is $61.62.

Add the flat $6.50 WA BCC and the high total is $1,300.52. Listed totals use that full plan review (200% of DFI), not the STFI 40% plan-review / ~140% of DFI path.

Simple, prescriptive, or ground-level decks may qualify as STFI with ~140% of DFI (100% building permit + 40% plan review) instead of 200% of DFI. Alternate paths not used in listed totals: STFI / simple-prescriptive / ground-level decks at ~140% of DFI (no published amount); decks under 30 inches above grade that may not need a building permit (no published amount).

No separate STFI dollar total is listed. Decks over 30 inches above grade generally need a building permit.

A deck under 30 inches above grade may not need a building permit, and that path is not assumed in the official bands. These figures are the building-permit portion only.

Confirm deck height, STFI eligibility, and current SDCI fees with SDCI before filing.

Decks over 30 inches above grade generally need a building permit. Building-permit portion only (200% of DFI + 5% technology SMC 22.900A.100 + $6.50 WA BCC RCW 19.27.085) using Seattle SDCI 2026 Fee Subtitle Tables D-1 and D-2 (retrieved 2026-10-18). Listed bands: low valuation $8,000 → $924.2; typical $12,000 → $1058.6; high $19,200 → $1300.52. Totals assume full plan review (200% of DFI), not STFI/ground-level (~140% of DFI) – that alternate path is not included in the official typical/low/high. Decks under 30 inches above grade may not need a building permit (no published amount).

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2 Retrieved Oct 18, 2026.

Kitchen remodel

Fee basis: Based on project value.

Project value for the formula: low $15,000, typical $35,000, high $75,000.

  • Typical $35,000: Tables D-1 and D-2 set DFI at $864 (Seattle SDCI 2026 Fee Subtitle, SMC 22.900; source retrieved Oct 18, 2026).

On the official path the building permit is 100% of DFI and plan review is 100% of DFI. That is the full plan-review path: 100% building permit + 100% plan review of DFI, or 200% of DFI.

It is not the STFI 40% plan-review path used for like-for-like reroofs. Building plus plan review is the $1,728 building+plan subtotal.

The technology fee is 5% of that $1,728. The WA State Building Code Council fee is a flat $6.50 when a building permit is issued, at low, typical, and high.

Add the official pieces: DFI $864, building permit $864 + plan review $864 (100% of DFI) + technology $86.40 (5%, SMC 22.900A.100) + WA BCC $6.50 (RCW 19.27.085) = $1,820.90. That is the official typical fee at the $35,000 typical project value.

  • Low $15,000 valuation = $1,159.40 total ($549 building + $549 plan + $54.90 tech + $6.50 WA BCC).

At $15,000 the DFI is $549. Building permit $549 plus plan review $549 is $1,098.

Technology is 5% of $1,098, which is $54.90. Add the flat $6.50 WA BCC and the low total is $1,159.40.

The high $75,000 valuation = $3,096.65 total ($1,471.50 building + $1,471.50 plan + $147.15 tech + $6.50 WA BCC). At $75,000 the DFI is $1,471.50.

Building permit $1,471.50 plus plan review $1,471.50 is $2,943. Technology is 5% of $2,943, which is $147.15.

Add the flat $6.50 WA BCC and the high total is $3,096.65. Listed totals use that full plan review (200% of DFI), not the STFI 40% plan-review path used for like-for-like reroofs.

Like-for-like reroofs use plan review at 40% of DFI; this kitchen remodel uses full plan review instead. Cosmetic cabinet-only same-layout work may not need a building permit.

Alternate paths not used in listed totals: separate electrical (Table D-14 / OTC), King County Public Health plumbing (not SDCI), and separate mechanical (Table D-8 / D-2 if range hood or HVAC changes are not in the building plans). Those amounts were not listed as fee lines.

These figures are the building-permit portion only. Confirm the kitchen permit path with SDCI before filing.

Building-permit portion only (200% of DFI + 5% technology SMC 22.900A.100 + $6.50 WA BCC RCW 19.27.085) using Seattle SDCI 2026 Fee Subtitle Tables D-1 and D-2 (retrieved 2026-10-18). Listed bands: low valuation $15,000 → $1159.4; typical $35,000 → $1820.9; high $75,000 → $3096.65. Real kitchen jobs almost always add separate electrical (Table D-14 / OTC) and King County Public Health plumbing permits – those amounts are not listed here and are not included in the official typical/low/high. Cosmetic cabinet-only same-layout work may not need a building permit.

Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2 Retrieved Oct 18, 2026.

Questions about these permit fees

How much is a roof replacement permit in Seattle?

The typical permit fee is $742.97. The range is $648.89 to $978.17. Fee basis: Based on project value. Project value for the formula: low $8,000, typical $12,000, high $22,000. Source: Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2. Retrieved Oct 18, 2026.

How much is an HVAC replacement permit in Seattle?

The typical permit fee is $126.73. The range is $63.37 to $190.10. Fee basis: Flat fee. Project value on this row: $7,500. Source: Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Table D-8 (22.900D.090). Retrieved Oct 18, 2026.

How much is a deck permit in Seattle?

The typical permit fee is $1,059. The range is $924.20 to $1,301. Fee basis: Based on project value. Project value for the formula: low $8,000, typical $12,000, high $19,200. Source: Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2. Retrieved Oct 18, 2026.

How much is a kitchen remodel permit in Seattle?

The typical permit fee is $1,821. The range is $1,159 to $3,097. Fee basis: Based on project value. Project value for the formula: low $15,000, typical $35,000, high $75,000. Source: Seattle SDCI 2026 Fee Subtitle (SMC 22.900), Tables D-1 and D-2. Retrieved Oct 18, 2026.

Where do I apply for a building permit in Seattle?

Apply with Seattle Department of Construction and Inspections (SDCI). The permit portal is https://cosaccela.seattle.gov/portal/.

Permit fees in other cities in the West

Related pages